General Schedule of Events

PHASE I

  1. Temporary Power Installed
  2. Trash Container Delivered
  3. Port-O-Let Delivered
  4. Surveying
  5. Utility Locates
  6. Tree/Stump removal (if necessary)
  7. Excavation
  8. Soils Analysis – open hole inspection by engineer
  9. Foundation Set-up and Pour
  10. Peripheral Drain Installation
  11. Backfill and Grading
  12. Garage Flatwork

PHASE II

  1. Exterior Utilities – water, sewer, gas, electric Utility Inspection
  2. Order Framing Material
  3. Order Windows
  4. Order Doors
  5. Order Trusses
  6. Order Steel and Posts
  7. Plumbing Base Installed
  8. Basement and Garage Flat Work
  9. Rough Framing
  10. Trusses Delivered and Installed
  11. Windows Delivered and Installed
  12. Fireplace Installation
  13. Siding or Stucco Installation
  14. Gutters and Downspouts
  15. Roofing Installation
  16. Exterior Flat Work City Sidewalk Inspection
  17. Heating/Air-Conditioning – duct and vent
  18. Plumbing – waste/vent and water
  19. Electrical – rough and service
  20. Inside Gas
  21. Framing Inspection

PHASE III

  1. Insulation
  2. Order Cabinets
  3. Order Trim Material
  4. Order Lighting
  5. Drywall Installation, Finish and Texture
  6. Masonry – Brick or Cultured Stone
  7. Interior and Exterior Paint
  8. Hardwood Floors
  9. Vinyl and Tile Floors
  10. Ceramic Wall Tile
  11. Trim Material Delivery and Installation
  12. Cabinet Delivery and Installation
  13. Counter Top Installation
  14. Lighting Delivery
  15. Plumbing Trim
  16. Electrical Trim
  17. Heating/Air-Conditioning Trim
  18. Appliances Delivery and Installation
  19. Carpet Installation
  20. Hardwood Floors Final Finish
  21. Mirrors and Shower Enclosures
  22. Touch-up
  23. Cleaning
  24. Fireplace Trim
  25. Walk-thru to prepare punch list (if any)
  26. Final Building Inspection